Construction Updates


Water/Sewer Utility Work


Project Areas/Updates
  • Beechwood Drive from 2746 Beechwood to Lake Drive (669 feet of 6-inch cast iron in 1926). Update: Completed.
  • Oakwood Drive from Conlon Avenue to Lake Drive (1,498 feet of 6-inch cast iron installed in 1926). Update: All necessary service lines have been replaced. The street will be a mill/overlay project for spring 2020.
  • Elmwood Drive from Conlon Avenue to Lake Drive (1,617 feet of 6-inch cast iron installed in 1926). Update: All necessary service lines have been replaced and the last remaining fire hydrant has been replaced. The street will be a mill/overlay project for spring 2020.
  • Boston Street from Conlon Avenue to Lake Grove Avenue (816 feet of 6-inch cast iron installed in 1929). Update: Completed.
  • Eastlawn Road from Hall Street to Anderson Drive (409 feet of 6-inch cast iron installed in 1929). Update: Completed.
Download copy of Temporary Service Line Water Shut Off Notice

**As a reminder, project areas will be milled and paved this coming spring with the exception of Beechwood and Eastlawn**

Click here for notice.
Contractor: Fer Pal
What is water main CIPP?
CIPP is a trenchless process to rehabilitate water mains. This process is less invasive and less disruptive than open cut utility replacement. Before the existing water main is removed from service, a temporary above ground water service system is put into place. Once the temporary system is in place and has passed required testing, the contractor will contact residents to remove water meters from homes before connecting to this system. The existing water main is then taken out of service. Access pits, which EGR DPW crews will have pre-excavated, are used to access segments of the water main. At these sites the contractor cleans the water main with a metal chain reamer and inspects the pipe with closed-circuit television to map water service locations. After this is completed, plugs are inserted at water service locations by specialized robotic equipment. Then the new liner is inserted, epoxy resin is injected and hot water is circulated to cure the new liner into the new structural pipe within the old (host) pipe. When this is completed, hydrostatic pressure testing is conducted, water services are reinstated, and the new pipe is disinfected, flushed and tested. Water services are then brought back into service, water the contractor contacts residents to reinstall water meters and the temporary system is removed. Restorations are then completed in the project areas. Water service lines that the City owns (between the main and the stop box/shut off in the public right-of-way) that need replacement will take place this summer, fall and into the winter.

For more technical information or FAQ’s with respect to the water main CIPP product/process, please visit the following link provided below:
http://www.aqua-pipe.com/frequently-asked-questions.html

Sanitary Sewer Rehabilitation:
Contractor: Corby Energy Services - Project Manager Josh Freeman (734) 604-5109

The following areas will receive sanitary sewer rehabilitation starting in the end of January and into February of 2020. Notices will be sent in advance of work, and door hangers will be utilized by the city's contractor Corby Energy Services. Schedule updates will be in BOLD.

Project areas:
  • Manhattan LANE - west of Manhattan Rd. at e. end (xlots) - Completed
  • Lake Pointe Dr. - Edgemere Dr. then west - Completed
  • Lake Drive - n. of Elmwood (SPOT REPAIR) - Delayed
  • Boston St. - west of York/Lake Grove to Breton - Completed
  • Lakewood Dr. - n. and s. of Cotswold LN , and w. on Cotswold LN - Completed
  • Albert St. - Lake Grove to Andover LN - Completed
  • Tenway Dr. - w. of Englewood Ave. - Completed
  • Oakwood Drive - Conlon Ave then west, one section - Completed
  • Oakwood Drive - east of Conlon Ave and west Lake Drive - Completed 
  • Oakwood Drive - Lake Drive to Woodcliff Drive - Completed
  • Elmwood Drive - east of Conlon Ave. and west of Woodlawn, one section - Completed
  • Argentina Drive - San Lucia Dr. then east, one section - Completed 
  • Richards Drive - east of Groton Rd. to east of Lake Grove Ave. - Completed
  • Richards Drive - west of Conlon Ave. to Conlon Ave. - Completed
  • Lovett Ave - Wealthy St to Greenwood Ave - April 1st 
Storm Sewer Rehabilitation:
Contractor: Corby Energy Services - Project Manager Josh Freeman (734) 604-5109

The following areas will receive storm sewer rehabilitation starting in the end of January and into February of 2020. Notices will be sent in advance of work, and door hangers will be utilized by the city's contractor Corby Energy Services. Schedule updates will be in BOLD.
  • Bellclaire Ave. - north of Frederick (xlots) - Delayed
  • Kenesaw Dr. - between Hall St. and Keneberry Way - Completed 

Notices for Utility Projects

Residents in impacted areas will receive notices through mail and/or by door hangers. Notices will be posted below as they are sent out.
Water Main Lining Letter of Work Intent
Water Meter Access Letter
Spring 2020 Sanitary Sewer CIPP Notice
Water Hydrant Flushing Notice
Elmwood Storm Sewer Notice
Oakwood Storm Sewer Notice

Street and Side Construction Updates


  • In 2015, City residents passed a ballot proposal to allow the City to collect 2.0 mills for street and sidewalk improvements. Since the passing, the City has worked aggressively to upgrade the 47 miles of street and 80 miles of sidewalk within the City.
  • Construction projects are subject to change depending on bid results and allocated funds. 
The Cost of Timely Maintenance
Proper street maintenance and surface preservation treatments at the right time (per PASER asset condition rating) is important to maintain the street surface condition, maximizing the impact of investment, while extending the life of the street asset.

Michigan Transportation Asset Management Council

The Michigan Transportation Asset Management Council (TAMC) provides best practices for road preservation based on a roads specific PASER rating. The city uses these best practices when deciding how to best preserve the lifespan of our roads. Please click here to see the recommended surface treatments in accordance to PASER ratings, and click here to go to the Michigan Transportation Asset Management Council's website.



 2020 Road Project Maps

*More information on dates of work will be posted in advance once that information becomes available*
*Once work begins, updates will be posted on this page weekly*

2020 Mill/Overlay Streets

A “mill & overlay” is a street maintenance process that requires the removal of the top layer of a street by a milling machine. After the top layer is removed any road base repairs are completed. Before the new pavement is placed, the surface of the newly milled pavement is covered with a liquid asphalt tack coat to bond the old and new pavements before a new layer of bituminous pavement is put in place. Mill and overlay projects at various depths are designated for streets that meet PASER 2-4 ratings. Spot curb replacement, drainage issues and some ADA ramps are also typically addressed during mill/overlay projects. This type of work will be done in the following areas:
  • Woodcliff Drive (Maplewood Drive to South City Limit)
  • Boston Street (Conlon Avenue to Breton Road)
  • Richards Drive (Conlon Avenue to Lake Grove Avenue) 
  • Elmwood Drive (Lake Drive to Breton Road)*
  • Oakwood Drive (Lake Drive to Breton Road)
  • Argentina Drive (Pinecrest Avenue to Plymouth Road)*
  • Lovett Avenue (Lake Drive to Greenwood Avenue)
  • Croswell Avenue (Lake Drive to Wealthy Street)
  • Lakeside Drive (Wealthy Street to Lake Drive)
  • Pioneer Club Road (Reeds Lake Boulevard to Manhattan Road)**
  • Idema Drive (Wren Avenue to Hall Street)
*bid alternates include neighborhood traffic circles for potential consideration
**Will be included in the FY 19/20 bid and award but will be approved for mill and overlay in fall of FY 20/21 to coordinate with water main utility rehabilitation


2020 Capeseal Streets

In the cape seal process an engineered polymer-modified RCRI is applied on the existing pavement and then covered with Micro-Surfacing. This is a cost-effective process that provides the strength and durability of RCRI and the smoothness and texture of micro-surfacing and/or slurry seal. A cape seal is applied when the pavement deterioration is greater than what a slurry seal or micro-surfacing is designed to correct, yet the pavement has not deteriorated to the point of requiring an expensive asphalt overlay. A cape seal prevents water penetration, reducing subsequent damage to the road bed, along with providing a new wearing surface. Cape seals are applied to streets rated PASER 4/5 to 6 depending on additional pavement surface maintenance. Cape seals can be used on residential streets as well as rural and urban highways. Used with crack sealing and necessary surface repairs, a cape seal significantly extends the life of a pavement. In advance of this treatment the City prepares the existing road surface by milling and paving out rough surface areas and performing crack sealing. This advance preparation work usually takes 1-2 days and is completed with appropriate traffic control. Please expect traffic delays on these streets, and please be courteous and respectful of crews on site controlling traffic. This type of work will be done in the following areas:


  • Groton Road (Richards Drive to Boston Street)
  • Lansing Street (Lakeside Drive to End)
  • Lakeside Drive (Lansing Street to Greenwood Avenue)
  • Reeds Lake Boulevard (Rexford Drive to Pioneer Club Road)

2020 Micro-Surface Streets

Micro-surfacing, a cost-effective pavement maintenance process used by DOT's and municipalities across the country, is a design mixture of polymer-modified asphalt emulsion, crushed aggregate, mineral fillers, water, and additives. The mixture is properly proportioned, mixed, and uniformly spread over a suitably prepared surface. Micro-surfacing is a pavement preservation treatment for street surfaces rated at PASER 5 or 6. Micro-surfacing provides a quality wearing surface, extends pavement life, sets within a day, seals out moisture and does not require utility casting adjustments. In advance of this treatment the City prepares the existing road surface by milling and paving out rough surface areas and performing crack sealing. This type of work will be done in the following areas:
  • Ridgewood Avenue (Maplewood Drive to End)
  • Oakwood Drive (Lake Drive to Woodcliff Drive)
  • Orchard Avenue (Burchard Street to End)
  • Burchard Street (San Jose Drive to Orchard Avenue)
  • San Lucia Drive (Argentina Drive including both arms to San Lu Rae Drive)
  • Cambridge Drive (Alexander Road to South End)
  • Gladstone Drive (Pontiac Road to Franklin Street)
  • Cambridge Boulevard (Franklin Street to Lake Drive)
  • Sherman Street (Rosewood Avenue to Cambridge Boulevard)
  • Edgemere Drive (Lake Point Drive to End)
  • Bagley Avenue (Lake Drive to Wealthy Street)
  • Arlington Drive (Cascade Road to End)

Sidewalk Construction 


As part of the 2015 Streets and Sidewalks Millage the City has been investing more funds into the annual sidewalk rehab and replacement program. Each year, targeted areas are investigated on a rotation basis. The targeted area is subject to budget constraints. 

Preventative Maintenance 


Streets that are not marked for construction this summer may still receive preventative maintenance if necessary. City DPW crews or contractors crack seal and/or apply mastic to PASER rated streets that are rated 6/7 throughout the spring and summer seasons. Please see the updated PASER map above for designated street ratings.

Notices

Notices are mailed to residents on affected streets in advance of any work. Notices will be posted below as they are being mailed out.
FY 19-20 Sidewalk replacement notice to impacted residents 
Argentina/Pinecrest Traffic Circle Notice


Construction

Street & Sidewalk Millage 



On May 5, 2015, East Grand Rapids voters approved a 10-year, 2.0-mill Streets and Sidewalks Millage request. The city updates our progress towards our 70% goal each fall after the construction season to benchmark our progress. The City has 47.26 miles of streets. Below is a graph of our current progress reflecting the road work completed this summer of 2019. The new PASER map can be downloaded here.


2019 Street Millage Paser Rating Graph

  • Blue line shows road condition projection if no additional funding was received.  
  • Green line projects road conditions through the 10-year period of the Street & Sidewalk Millage using the additional 2.0 mills approved by East Grand Rapids voters. 
  • Red line shows current ratings with approved millage. 

DTE Private Utility Gas Main Projects 2020

DTE Energy will be continuing their Gas Renewal Project (GRP) throughout multiple areas of the city. Please download the links below for more information:

Map of DTE work areas with project timeline dates
"Appointment Needed" Door hanger
DTE Mailer to residents
"Relight for Distribution" Door hanger
"Upgrade Completed" Door hanger

For any questions or complaints, please call DTE at 616-551-2621.


 

Information Links:



Questions regarding the East Grand Rapids Streets & Sidewalk millage can be directed to 616-949-2110 or to City Clerk Karen Brower by email or to 750 Lakeside Drive SE, EGR MI 49506.